Skip to main content
File #: O-244-25    Version: 1 Name:
Type: Ordinance Status: Agenda Ready
File created: 5/15/2025 In control: Public Utilities Department
On agenda: 6/3/2025 Final action:
Title: Authorizing the appropriation and expenditure of $350,000 from the Sanitary Sewer Replacement Fund for the Aeration Tank Cleaning Project at the Bay View Water Reclamation Plant; authorizing the mayor to accept bids and award contracts to facilitate the Aeration Tank Cleaning Project; and declaring an emergency.
Date Ver.Action ByActionResultAction DetailsAgenda SummaryAudio
No records to display.

Label
DPU060325AERATIONTANKCLEANING
Water Reclamation
Mike Schreidah (x2607)
Revised

Title
Authorizing the appropriation and expenditure of $350,000 from the Sanitary Sewer Replacement Fund for the Aeration Tank Cleaning Project at the Bay View Water Reclamation Plant; authorizing the mayor to accept bids and award contracts to facilitate the Aeration Tank Cleaning Project; and declaring an emergency.

Body
SUMMARY & BACKGROUND:
The Bay View Water Reclamation Plant houses nine (9) aeration tanks, which are used for the activated sludge biological treatment process in the Secondary Treatment area. Each tank utilizes around 1200 air diffusers to provide oxygen to the microorganisms to break down the organics in the activated sludge treatment process. These air diffusers require routine cleaning and sometimes replacement in order to effectively diffuse the oxygen to the microorganisms. This Ordinance will provide funds to clean one aeration tank from accumulated sludge and perform required cleaning, repairs and/or replacement of parts such as, air diffusers, sleeves, clamps, piping and valves as needed. This cleaning project will increase the air diffusion efficiency which will optimize the generation of good mixed liquor for better clarification of water in the Secondary Clarifiers. Having good mixed liquor will help maintain compliance with the Plant's National Pollutant Discharge Elimination System (NPDES) discharge permit.

Summary
NOW THEREFORE Be it ordained by the Council of the City of Toledo:

SECTION 1. That the appropriation of up to $350,000 from the unappropriated balance of the Sewer Replacement Fund is authorized to Account Code 6073-36000-4UC1925STDSTD for the completion of the Aeration Tank Cleaning Project at the Bay View Water Reclamation Plant; and the expenditure of the same is authorized.

SECTION 2. That the Mayor is authorized to accept bids and award contracts for the cleaning of one aeration tank from accumulated sludge and for t...

Click here for full text