Label
DPU061620SidewalkResolution
Division of Engineering Services
Karl Huss (x2847)
(Revised)
Title
Providing for the rehabilitation of sidewalks and driveway approaches on various streets in the City of Toledo; and declaring an emergency.
Body
SUMMARY & BACKGROUND:
The following resolution is procedurally required to allow for the repair or construction of new sidewalks in conjunction with our annual sidewalk rehabilitation program. By attending to the rehabilitation of sidewalks, we will be limiting the city's liability and maintaining this important asset for the benefit of our citizens. The Capital Improvement Program (CIP) budget allocates $1,000,000 for city responsibility which includes sidewalks damaged or raised by city-owned tree roots and the installation of pedestrian curb ramps. The proposed assessed sidewalk budget allocates $1,232,000 for sidewalk rehabilitation to be assessed to the property owners.  It is necessary to perform both city responsibility and property owner assessed sidewalks together in this program since the rehabilitation is completed in conjunction with one another. The following resolution will begin the assessment process and provide notice to those property owners needing to rehabilitate their sidewalk in accordance with the city's sidewalk policy.  The locations targeted for this year's program are as follows.
Summary
NOW, THEREFORE, Be it resolved by the Council of the City of Toledo:                        
	SECTION 1.	That the concrete sidewalk and driveway approaches be rehabilitated at the following locations throughout the city:
4707 N MAY AVE		1430 KEDRON ST		625 COLLINS ST
4232 HURLEY DR		805 WOODSDALE AVE	2484 SCOTTWOOD AVE
1401 LUSCOMBE DR	4325 DEERWOOD LN	665 NESSLEWOOD AVE
3456 MAPLEWAY DR	719 LODGE AVE		627 ISLINGTON ST
3661 BEECHWAY BLVD	1782 ARLINGTON AVE	619 COLLINS ST
3412 BEVERLY DR		742 LEONARD ST		2855 MULBERRY ST
3934 RUGBY DR		1935 TALBOT ST		675 WOODLAND AVE
3428 BEVERLY DR		1207 FREEDOM ST		9...