File #: O-059-26    Version: 1 Name:
Type: Ordinance Status: Approved
File created: 2/12/2026 In control: Public Utilities Department
On agenda: 3/3/2026 Final action: 3/3/2026
Title: Authorizing the Mayor to enter into a one (1) year agreement with the option to renew for up to three (3) additional one-year periods with Buckeye Pumps for the purpose of providing repair service for the Spent Lime Dewater Facility pre-fill tank mixer; authorizing the expenditure from the Water Operating Fund in an amount not to exceed $40,000 annually; waiving the competitive bidding provisions of TMC Chapter 187; and declaring an emergency.

Label
DPW030326REPAIROFSPENTLIMEDEWATERFACILITYPREFILLTANKMIXER
Water Treatment
Andy McClure (7866)
Revised

Title
Authorizing the Mayor to enter into a one (1) year agreement with the option to renew for up to three (3) additional one-year periods with Buckeye Pumps for the purpose of providing repair service for the Spent Lime Dewater Facility pre-fill tank mixer; authorizing the expenditure from the Water Operating Fund in an amount not to exceed $40,000 annually; waiving the competitive bidding provisions of TMC Chapter 187; and declaring an emergency.

Body
SUMMARY & BACKGROUND:
The project takes place at the City of Toledo's Spent Lime Dewatering Facility, where spent lime is processed into a reusable solid form. The facility operates two presses, handling approximately 250,000 gallons of spent lime per day. The spent lime entering the presses has a solid content of 4-5%, which increases to 45-50% after processing. A mixer is used to keep solids suspended. If the mixer malfunctions, the solids content drops to about 3-4% before pressing. Higher solid content going into the presses results in a higher percentage of solids coming out. Currently, only one mixer is in operation, and there is no functional spare available if it fails.

Summary
NOW THEREFORE Be it ordained by the Council of the City of Toledo:

SECTION 1. That the Mayor is authorized to enter into a one (1) year agreement with the option to renew for up to three (3) additional one-year periods with Buckeye Pumps for the purpose of repair services for the Spent Lime Dewater Facility pre-fill tank mixer, located at the Collins Park Water Treatment Plant, upon terms and conditions acceptable to the Director of Public Utilities and the Director of Law.

SECTION 2. That the expenditure of an amount not to exceed $40,000 annually, subject to appropriation in future years, is authorized from the Water Operating Fund, Account Code 6060-32000-4000505STDSTD for the purposes authorized i...