Label
DPU 021318SPENT LIME REMOVAL/HAULING/DISPOSAL
DPU/Water Treatment
P. Bannister (x1846)
Revised
Title
Authorizing the expenditure of an amount not to exceed $4,500,000 in the Water Operating Fund for the removal, hauling and beneficial reuse of spent lime produced by the Division of Water Treatment; authorizing the Mayor to accept bids and execute the necessary contract or contracts; and declaring an emergency.
Body
SUMMARY & BACKGROUND:
Spent lime is a byproduct of the water treatment process. The reuse and disposal of this material must be done in an environmentally responsible manner that is approved by the Ohio EPA. Funds are included in the proposed 2018 operating budget for this expenditure.
Summary
NOW, THEREFORE, Be it ordained by the Council of the City of Toledo:
SECTION 1. That the sum not to exceed $4,500,000 is authorized for expenditure from the Water Operating Fund Account Code 6060-32000-4000500STDSTD, subject to the availability and appropriation of funds, for the removal, hauling and beneficial reuse of spent lime produced by the Division of Water Treatment.
SECTION 2. That the Mayor is authorized to accept bids and to execute necessary contracts for the removal, hauling and beneficial reuse of spent lime produced by the Division of Water Treatment upon such terms and conditions as approved by the Director of Public Utilities and the Director of Law.
SECTION 3. That the Director of Finance is authorized to issue his warrant or warrants against the Account Code identified in Section 1 above in an amount not to exceed $4,500,000 in payment of the obligations incurred pursuant to the contracts authorized in Section 2 above upon presentation of proper voucher or vouchers.
SECTION 4. That various adjustments and line item expenditures and transfers are authorized to comply with said contracts/agreements.
SECTION 5. That this Ordinance is declared to be an emergency measure and shall be in force and effect from and af...
Click here for full text