Authorizing the Mayor to enter into a contract for the repairs of multiple crane units at the Water Treatment Plant; authorizing the expenditure of an amount not to exceed $26,000 from the Water Treatment Plant operating fund; waiving the competitive bidding provisions of TMC Chapter 187; and declaring an emergency.
Body
SUMMARY & BACKGROUND:
The City utilizes multiple crane units at the Collins Park Water Treatment Plant and Low Service Pump Station to support maintenance, repair, and equipment handling operations. A recent inspection by a qualified Crane 1 Services, Inc. (Crane 1) technician identified multiple safety and compliance-related deficiencies requiring repair, including issues with hoist brakes, load cables/wire ropes, control stations, crane frames and bumpers, and hoist gear boxes. The proposed repairs are necessary to address these deficiencies and maintain the safe and reliable operation of the crane units.
It is requested that the competitive bidding requirements be waived and the repairs be awarded to Crane 1. Since Crane 1 has already completed the inspection and identified the specific deficiencies, utilizing another vendor would require that vendor to conduct its own inspection before determining the necessary repairs and associated costs. This would result in duplication of inspection services, additional costs, and delays in completing the required repairs.
Summary
NOW THEREFORE Be it ordained by the Council of the City of Toledo:
SECTION 1. That the Mayor is authorized to enter into a one (1) year agreement with Crane 1 Services, Inc. for the repair of the multiple crane units at the Water Treatment Plant, upon terms and conditions acceptable to the Department of Public Utilities and the Director of Law.
SECTION 2. That the expenditure of an amount not to exceed $26,000 is authorized from the Water Operating Fund, Account Co...