Legislation Details

File #: REF2610    Version: 1 Name:
Type: Referral Status: Answered Referral
File created: 1/15/2026 In control: Clerk's Office
On agenda: 1/13/2026 Final action: 1/29/2026
Title: From: Councilman Sarantou Response Requested: 1/20/26 Please give a progress report as to what has been done on the Arlington Ave Sewer Collapse, and an estimated timeline on when this project will be concluded.
Sponsors: George Sarantou
Date Ver.Action ByActionResultAction DetailsAgenda SummaryAudio
No records to display.

Label

Councilman Sarantou

Agenda Review

Arlington Sewer Project

1/13/2026

 

 

Title

From:   Councilman Sarantou                      Response Requested:                      1/20/26

 

Please give a progress report as to what has been done on the Arlington Ave Sewer Collapse, and an estimated timeline on when this project will be concluded.

 

 

Body

Referral Response:

 

1/21/26 Arlington Sewer Replacement Update:

Finish Bore Pit including mobilizing equipment-January 30

Begin Jack and Bore 48” pipe Atlantic to Francis - February 2

Begin Jack and Bore 48” pipe Atlantic to Woodsdale - February 2

Project Completion Date: July 17, 2026