File #: O-024-26    Version: Name:
Type: Ordinance Status: Agenda Ready
File created: 12/19/2025 In control: Public Utilities Department
On agenda: 1/20/2026 Final action:
Title: Authorizing the appropriation and expenditure of an amount not to exceed $431,954 from the Water Replacement Fund and an amount not to exceed $431,954 from the Sanitary Sewer Replacement Fund to provide as needed professional services necessary to continue program management duties related to the AMI Program, as well as associated miscellaneous coordination, billing, and data analysis; authorizing the Mayor to enter into contract for professional services; waiving the competitive bidding provisions of TMC Chapter 187 for said purpose; and declaring an emergency.
Date Ver.Action ByActionResultAction DetailsAgenda SummaryAudio
No records to display.

Label

DPU012026DLZSERVICES

Public Utilities

Douglas Stephens (x1847)

Revised

 

Title

Authorizing the appropriation and expenditure of an amount not to exceed $431,954 from the Water Replacement Fund and an amount not to exceed $431,954 from the Sanitary Sewer Replacement Fund to provide as needed professional services necessary to continue program management duties related to the AMI Program, as well as associated miscellaneous coordination, billing, and data analysis; authorizing the Mayor to enter into contract for professional services; waiving the competitive bidding provisions of TMC Chapter 187 for said purpose; and declaring an emergency.

 

Body

Since 2021, the Department of Public Utilities has utilized DLZ Ohio, Inc (DLZ) to provide professional program management and associated services for the AMI Project.  Throughout this 4-year period DLZ’s program management team has been instrumental in ensuring these projects have been successfully completed by performing duties that the City did not have the capacity to staff with Department of Public Utilities personnel.  There are still approximately 5,500 meters that need installed to completely finish the AMI program, but these meters have more difficult installation issues and were unable to be completed under the AMI project.  As an extension of working on the AMI project, DLZ staff has gained extensive detailed knowledge of new software systems, billing, customer service, and meter shop operations that make them uniquely suited to continue with the management of work related to these functions of the Department of Public Utilities.  As a result, the department intends to utilize DLZ to complete the meter installations and other tasks as needed that have been associated with the AMI project. 

 

Summary

NOW THEREFORE Be it ordained by the Council of the City of Toledo:

 

                     SECTION 1. That the appropriation of an amount not to exceed $431,954 is authorized from the unappropriated balance of the Water Replacement Fund into Account Code 6063-31000-4UC0226STDSTD and an amount not to exceed $431,954 is authorized from the unappropriated balance of the Sanitary Sewer Replacement Fund into Account Code 6073-31000-4UC0226STDSTD and the expenditure of the same is authorized for professional services necessary to continue program management duties related to the AMI Program.

                     

                     SECTION 2. That the Mayor is authorized to enter into contract(s) for as needed professional services upon such terms and conditions that are acceptable to the Director of Public Utilities and the Director of Law.

                     

                     SECTION 3. That this Council finds and determines it is in the best interest for the City to waive all competitive bidding provisions of TMC Chapter 187 in order to allow DLZ to continue to provide professional services related to the AMI Project.

 

                     SECTION 4. That the Finance Director is authorized to issue their warrant or warrants against the above listed account codes in an amount not to exceed $863,908 in payment of the obligations authorized above upon presentation of proper voucher or vouchers.

 

                     SECTION 5. That the disappropriation of any remaining budget to fund balance is authorized at project closeout.

 

                     SECTION 6. That this Ordinance is declared to be an emergency measure and shall be in force and effect from and after its passage. The reason for the emergency lies in the fact that same is necessary for the immediate preservation of the public peace, health, safety, and property, and for the further reason that the Ordinance must be immediately effective to allow DLZ to continue working on the project.

 

 

 

                     Vote on emergency clause:  yeas _____, nays _____.

 

                     Passed:  _________________, as an emergency measure:  yeas _____, nays _____.

 

 

Attest:  ________________________                                              __________________________________

                            Clerk of Council                                                                           President of Council

 

                     

Approved:  _____________________                                          __________________________________

                                                                                                                                                                                                   Mayor

 

 

                     I hereby certify that the above is a true and correct copy of an Ordinance passed by Council ________________________.

 

 

Attest:  ________________________

                    Clerk of Council