Title: What was the total amount budgeted for the Lewis Avenue construction, and what were the cost overages for the Culvert issue.
Sponsors: Katie Moline
Date Ver.Action ByActionResultAction DetailsAgenda SummaryAudio
No records to display.

Label

MOLINE

STREETS, PUBLIC SERVIC & UTILITEIS

1/16/2024

 

Title

What was the total amount budgeted for the Lewis Avenue construction, and what were the cost overages for the Culvert issue.

 

Body

Referral Response:

 

 

Amount Budgeted: $4,816,878.80

 

Culvert extra:$105,000